COVID-19: Most multifamily contractors experiencing delays in projects due to coronavirus pandemic

Coronavirus

COVID-19: Most multifamily contractors experiencing delays in projects due to coronavirus pandemic

NMHC survey traces the impact of COVID-19 on multifamily construction permitting, starts, completions, materials, and labor.


By ROBERT CASSIDY, EXECUTIVE EDITOR | April 5, 2020
NMHC survey of multifamily GCs delays

The NMHC found that the majority of the 135 multifamily contractors surveyed had experienced delays with apartment or condominium projects due to the COVID-19 pandemic.

   

Washington, D.C., April 3, 2020 – More than half of respondents (55%) to a new survey on multifamily construction by the National Multifamily Housing Council (NMHC) said that they were experiencing construction delays in the jurisdictions where they operate.

The NMHC Construction Survey is intended to gauge the magnitude of the disruption caused by the COVID-19 outbreak on multifamily construction. The survey, which had 135 respondents, also determined that:

  • Of the 55% experiencing delays, 76% were dealing with delays in permitting and 59% in starts
  • About a quarter (24%) of respondents said a lack of materials was affecting their construction operations
  • 41% of respondents said that COVID-19 outbreak-related labor constraints were affecting construction operations

 

The NMHC found that the majority of the 135 multifamily contractors surveyed had experienced delays with apartment or condominium projects due to the COVID-19 pandemic.

 

NMHC survey - moratorium delayMore than three-fifths (62%) of respondents said they had been delayed due to construction moritoriums.

 

MULTIFAMILY CONTRACTORS TRYING NEW STRATEGIES TO COPE WITH COVID-19 IMPACT

The NMHC Construction Survey also found that nearly three-fourths (73%) of construction firm respondents said that they have implemented new strategies to deal with the hurdles caused by the pandemic. These include sourcing materials from alternative locations (43%), staggering shifts to reduce on-site exposure (52%), and using technology to replace in-person transactions like inspections and approvals (67%).

 

NMHC survey - new GC strategies for copingThe NMHC survey found that multifamily contractors had adopted many new strategies for coping with delays in work due to the coronavirus pandemic. Note: Respondents could check multiple items for this question.

 

NMHC will conduct this survey on a bi-weekly basis to provide an estimation of the impact of COVID-19 on multifamily construction. Additional NMHC-produced resources focused on the COVID-19 outbreak can be found here.

 

ABOUT THE NATIONAL MULTIFAMILY HOUSING COUNCIL

Based in Washington, D.C., the National Multifamily Housing Council (NMHC) brings together the prominent apartment owners, managers, and developers in the trillion-dollar apartment industry who provide apartment homes for 40 million Americans. For more information: 202/974-2300, e-mail the Council at info@nmhc.org, or visit NMHC's website: https://www.nmhc.org/.

Related Stories

Coronavirus | May 27, 2020

Clean is the new Green as U.S. hospitality sector inches closer to reopening

Three design firms share their takes on what will make customers more comfortable about returning.

Coronavirus | May 26, 2020

Multifamily developers report mounting delays in permitting and starts due to coronavirus pandemic

More than half (53%) of multifamily developer respondents reported construction delays in the jurisdictions where they operate, according to the third edition of the National Multifamily Housing Council (NMHC) COVID-19 Construction Survey.

Coronavirus | May 26, 2020

9 tips for mastering virtual public meetings during the COVID-19 pandemic

Mike Aziz, AIA, presents 9 tips for mastering virtual public meetings during the COVID-19 pandemic.

Coronavirus | May 22, 2020

Designing a health facility for the next pandemic

Planning with intent is the key to readiness, states Eppstein Uhen Architects, the guide’s author.

Coronavirus | May 22, 2020

COVID-19: Healthcare designers look to the future of medical facilities in light of coronavirus pandemic

The American College of Healthcare Architects (ACHA) has released the key findings of a survey of its members revealing their insights on the future of healthcare architecture and the role of design in the context of the COVID-19 healthcare crisis.

Coronavirus | May 18, 2020

Will empty hotels provide an answer for affordable housing shortage?

A Los Angeles-based startup sees the Midwest as most fertile for adaptive reuse.

Coronavirus | May 18, 2020

Infection control in office buildings: Preparing for re-occupancy amid the coronavirus

Making workplaces safer will require behavioral resolve nudged by design.

Coronavirus | May 18, 2020

Global design firms collaborate on new COVID-19 mobile testing lab to bring testing to vulnerable communities worldwide

Perkins and Will, Schmidt Hammer Lassen Architects, and Arup Group develop scalable solutions for increased testing capacity within high-density and under-served neighborhoods. 

Coronavirus | May 11, 2020

Experts offer a 13-point plan to reduce coronavirus deaths in nursing homes

Two nationally recognized experts in the design of senior living facilities offer a 13-point plan to protect our frailest citizens.

Glass and Glazing | May 8, 2020

Vitro Architectural Glass releases guide on decontaminating glass surfaces

The five-page technical document offers methods for cleaning and sanitizing glass surfaces. 

boombox1 - default
boombox2 -
native1 -

More In Category

MFPRO+ Special Reports

Top 10 trends in affordable housing

Among affordable housing developers today, there’s one commonality tying projects together: uncertainty. AEC firms share their latest insights and philosophies on the future of affordable housing in BD+C's 2023 Multifamily Annual Report.




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021