Cost of HVAC equipment to remain flat in 2009, says Turner

Cost of HVAC equipment to remain flat in 2009, says Turner


August 11, 2010
This article first appeared in the 200906 issue of BD+C.

While some manufacturers have announced slight increases in facilities equipment pricing for 2009, the average cost of equipment is expected to remain flat in 2009, according to the 2009 Turner Logistics Equipment Cost Index. However, equipment pricing could face increased pressure if there is a further decline in market demand.

Published by Turner Logistics, the facility equipment solutions arm of Turner Construction, the report tracks the average cost and lead time for common facilities equipment, including chillers, generators, cooling towers, and air-handling units.

Turner anticipates that lead times will continue to improve. Signs of production consolidation have been noted as manufacturers adjust workforce and production capacity.

 
Estimated lead times for HVAC equipment in 2009
(varies due to equipment sizing)
Cooling towers: 6–10 weeks Chillers: 12–20 weeks Air-handling units: 10–18 weeks Generators: 8–30 weeks Medium voltage switchgear: 12–18 weeks Uninterruptible power supply: 18–22 weeks

Related Stories

Energy Efficiency | Dec 5, 2018

Harvard debuts HouseZero as a possible response to making existing buildings more efficient

Hundreds of embedded sensors will inform energy use reduction research.

Building Technology | Oct 15, 2018

Construction continues to be vulnerable to cyberattacks

The latest report from eSentire finds a total of 4 million “hostile events” against all sectors during the spring months.

Building Technology | Sep 20, 2018

A new report tracks industry preferences for building documentation tools

More firms are adding scanning and photography to their services.

Sponsored | Market Data | Sep 17, 2018

Construction Contract Issues?

Building Technology | Sep 17, 2018

A future-ready office building for techie workers will soon spring up in New York City

Groundbreaking for the 20-story 14th@Irving is scheduled for early next year.

Building Technology | Sep 13, 2018

McKinsey report assesses where opportunities could lie in construction technology

McKinsey & Co. sees systems integration and talent acquisition as key investment drivers.

Modular Building | Aug 6, 2018

More contractors are turning to offsite production for speed and quality

Skender launches an advanced manufacturing division. Katerra ups its bet on modular. Prefabrication comes to the rescue on multiple projects.

Modular Building | Jul 23, 2018

Offsite construction: Why it’s important for the survival of your firm

The industry is approaching its “heart attack moment,” with so many large projects that are chronically late, over budget, and unprofitable, writes FMI Capital Advisors’ Michael Swistun.

Building Technology | Jul 17, 2018

Construction technology is catnip for investors

JLL, in a new report that tracks this trend, cites three areas where startups are most active.

boombox1
boombox2
native1

More In Category


Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021