Burr Elementary School

Burr Elementary School

Fairfield, Conn.


By Staff | August 11, 2010
This article first appeared in the 200505 issue of BD+C.

In planning the Burr Elementary School in Fairfield, Conn., the school's building committee heeded the words of William Wordsworth: Come forth into the light of things, let nature be your teacher.

They selected construction manager Turner Construction Company, New York, and the New York office of A/E firm Skidmore, Owings & Merrill to integrate nature on the heavily wooded 15.5-acre site into the day-to-day experiences of the K-5 school's 500 students.

SOM's design realized the town's vision of bringing the outdoors inside by organizing classrooms along the east and west edges of the building. This program allowed existing trees to remain in place, perforating the interior of the plan and creating a series of courtyards that serve as outdoor classrooms.

Separating the bus drop-off on the south side from the parent drop-off on the north obviated the need to build a perimeter road encircling the school. As a result, classrooms face out onto wooded areas instead of parking lots.

Getting the curvilinear courtyard walls right was critical to the success of the project and required the close collaboration of the Building Team and the steel fabricator, United Steel, East Hartford, Conn. The walls were made from insulated glass panels measuring 4×11.5 feet and 4×9.5 feet in an aluminum mullion system. The top of the curving courtyard was defined by a continuous 27-inch-deep curved steel beam that supported the roof decking above and anchored the top edge of the glass wall below.

Related Stories

K-12 Schools | Mar 29, 2022

A graceful design opens Pennsylvania’s Springfield High School to its community

Multifunctional spaces enhance student collaboration.  

K-12 Schools | Mar 8, 2022

Design delivers new media messages for schools

Media centers are no longer physically confined to one room.

Resiliency | Feb 15, 2022

Design strategies for resilient buildings

LEO A DALY's National Director of Engineering Kim Cowman takes a building-level look at resilient design. 

Coronavirus | Jan 20, 2022

Advances and challenges in improving indoor air quality in commercial buildings

Michael Dreidger, CEO of IAQ tech startup Airsset speaks with BD+C's John Caulfield about how building owners and property managers can improve their buildings' air quality.

K-12 Schools | Dec 27, 2021

A ‘new urbanist’ middle school takes shape in Austin

Design-build delivery, still rare for Texas school construction, fit expeditiously for this project.

K-12 Schools | Dec 10, 2021

Trends in K-12 school design, with Dan Boggio and Melissa Turnbaugh of PBK

Dan Boggio and Melissa Turnbaugh of PBK, the largest K-12 design firm in the U.S.,  discuss the favorable market conditions and the latest trends in K-12 school design with BD+C's Rob Cassidy.    

Giants 400 | Nov 18, 2021

2021 K-12 School Sector Giants: Top architecture, engineering, and construction firms in the U.S. K-12 school facilities sector

PBK, Gilbane, AECOM, and DLR Group head BD+C's rankings of the nation's largest K-12 school facilities sector architecture, engineering, and construction firms, as reported in the 2021 Giants 400 Report.

K-12 Schools | Nov 16, 2021

Massachusetts’ first net-positive energy public school opens

Part of the town of Westborough’s goal to be carbon-neutral by 2035.

K-12 Schools | Nov 14, 2021

New Blackwater Community School completed for Gila River Indian Community, in Arizona

Construction on the new Blackwater Community School, a two-story structure on the Gila River Indian Community, located southeast of Phoenix, Arizona, was completed on August 31, 2021.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021