flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

North American data center construction rises 25% to record high in first half of 2023, driven by growth of artificial intelligence

Data Centers

North American data center construction rises 25% to record high in first half of 2023, driven by growth of artificial intelligence

Pre-leasing rates exceed 70% in primary North American data center markets


By CBRE | September 21, 2023
North American data center construction rises 25% to record high in first half of 2023, driven by growth of artificial intelligence  - Image by Pete Linforth from Pixabay
Image by Pete Linforth from Pixabay

Demand for data center space overshadowed economic uncertainty and concerns around power availability in the first half of the year. Construction of North American data centers is at an all-time high in part due to the continued growth of artificial intelligence, according to CBRE. 

CBRE’s latest North American Data Center Trends Report found there is 2,287.6 megawatts (MW) of data center supply currently under construction in primary markets, reaching a new all-time high with more than 70% already preleased. At the same time last year, there was 1,830.3 MW under construction. Companies are leasing space up to 36 months in advance of construction completion in anticipation of future demand and to secure data center space at current pricing. 

“Data center construction is at an all-time high, driven by strong demand from all users, including AI, hyperscale and enterprise,” said Pat Lynch, executive managing director for CBRE’s Data Centers Solution. “New and existing uses of artificial intelligence cases grew tremendously in the first half of the year, and we expect demand to remain strong with AI driving leasing opportunities in the second half of the year.” 

Absorption in the eight primary U.S. data center markets* remained resilient in H1 2023, totaling 468.8 MW despite challenges within the supply chain. While supply increased 19.2% year-over-year, vacancy remains near a record low of 3.3%. Strong demand paired with a lack of available power and extended timelines have kept asking rental rates climbing. Average primary market asking rents rose to $147.80 per kW/month from $127.50 (a 15.9% year-over-year increase). 

Top Data Center Construction Markets 

Northern Virginia remained the most active data center market in the first half of 2023 with 918 MW under construction. The market set a record low vacancy rate of 0.94% while power improvement projects are underway. Separately, Chicago recorded a 125% spike in under-construction activity - the largest increase among all U.S. data center markets. 

“Most major markets are grappling with power constraints, and developers are facing challenges within their supply chain, but it’s not slowing down the demand for data center space,” said Gordon Dolven, director of Americas Data Center Research at CBRE. “Data center operators are prioritizing power availability, rather than selecting markets based on traditional factors such as location, connectivity, water and land pricing.”

Top 10 most active data center construction markets
MarketH1 2023 Total InventoryH1 2023 Under Construction
Northern Virginia2,254.1 MW918 MW
Hillsboro248.4 MW267.3 MW
Silicon Valley410.7 MW125 MW
Chicago367.5 MW205 MW
Dallas-Fort Worth499.4 MW273.3 MW
Phoenix360 MW163.5 MW
Toronto291.3 MW99.6 MW
New York Tri-State177.5 MW99.9 MW
Atlanta271 MW235.6 MW
Montreal135.5 MW106.5 MW
 

Other market highlights include Dallas-Fort Worth, which saw the greatest year-over-year increase in absorption of 327%, jumping to 110.6 MW from 25.89 MW. Hillsboro also experienced the largest inventory growth of all primary markets, increasing to 248.4 MW from 139.4 MW (78% year-over-year growth). 

To view the full report, click here.

Related Stories

Giants 400 | Aug 28, 2019

Top 50 Data Center Engineering Firms for 2019

Vanderweil, ESD, kW Mission Critical, Jacobs, and EXP head the rankings of the nation's largest data center sector engineering and engineering architecture (EA) firms, as reported in Building Design+Construction's 2019 Giants 300 Report.

Giants 400 | Aug 28, 2019

Top 35 Data Center Architecture Firms for 2019

Corgan, HDR, Gensler, AECOM, and Page top the rankings of the nation's largest data center sector architecture and architecture engineering (AE) firms, as reported in Building Design+Construction's 2019 Giants 300 Report.

Data Centers | Aug 9, 2019

This will be Central Florida’s largest data center

Baker Barrios Architects is designing the project.

Data Centers | Jul 25, 2018

Data centers keep cool while staying hot-hot-hot

Cooling mission critical facilities efficiently is critical to their operations and profitability.

Data Centers | Jun 22, 2018

Can this new data center concept combat climate change?

The concept has been dubbed The Spark.

Data Centers | Feb 22, 2018

Demand for ‘hyperscale’ data centers continues to grow; U.S. leads the way

The number of so-called “hyperscale” data centers worldwide surpassed 390 at the end of 2017, with 69 more facilities in the works, according to Synergy Research Group.

Giants 400 | Oct 16, 2017

Data center market forecast: Clearly cloudy

Look for mission-critical construction to double in the next few years.

Data Centers | Oct 13, 2017

Top 35 data center construction firms

Turner Construction Co., Holder Construction, and DPR Constrcution top BD+C’s ranking of the nation’s largest data center sector contractors and construction management firms, as reported in the 2017 Giants 300 Report.

Giants 400 | Oct 12, 2017

Top 30 data center engineering firms

Syska Hennessy Group, AECOM, and Morrison Hershfield top BD+C’s ranking of the nation’s largest data center sector engineering and EA firms, as reported in the 2017 Giants 300 Report.

Giants 400 | Oct 11, 2017

Top 25 data center architecture firms

Jacobs, Corgan, and Gensler top BD+C’s ranking of the nation’s largest data center sector architecture and AE firms, as reported in the 2017 Giants 300 Report.

boombox1
boombox2
native1

More In Category

Data Centers

What’s next for data center design in 2024

Nuclear power, direct-to-chip liquid cooling, and data centers as learning destinations are among the emerging design trends in the data center sector, according to Scott Hays, Sector Leader, Sustainable Design, with HED. 




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021