flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Prefab saves the day for Denver hospital

Building Team Awards

Prefab saves the day for Denver hospital

Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.


By Robert Cassidy, Executive Editor | April 10, 2015
Prefab saves the day for Denver hospital

An 8x25-foot multi-trade rack containing mechanical, piping, and HVAC systems is lifted into place at Saint Joseph Hospital, Denver, by mechanical subcontractor U.S. Engineering. Photo: Ross Cooperthwaite

This article first appeared in the April 2015 issue of BD+C.

The commission from the healthcare client, Exempla (now SCL Health), was straightforward: build us a 360-bed acute care replacement hospital in Denver with 21 ORs (two of them hybrids), 42 ED rooms (12 dedicated to eldercare), a 20,000-sf central utility plant, and 1,100 parking spaces. And, by the way, do it in 30 months.

Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.

Mortenson found that for every dollar spent on prefab, about 13% of the investment would be returned as a quantifiable benefit to the project. Prefabrication was also seen as the only way to complete the project within the client’s rigorous schedule.

The team went all-out on modularity. They physically tested four different mockups of shower pan systems before arriving at a trench drain system where the entire room floor sloped toward the drain. Based on an evaluation of a full bathroom pod mockup, the team determined that the ceiling height could be reduced from nine feet to seven feet, 11 inches, saving $110,000.

The bathroom provider, Oldcastle Modular Eggrock Pods, produced 440 pods, 257 of which went into patient rooms.

The team completed 376 headwalls entirely in a nearby warehouse, along with 250 multi-trade prefabbed mechanical racks, each measuring 8x25 feet.

The hospital, which is being operated jointly with National Jewish Health, opened on time earlier this year.

 

PROJECT SUMMARY
HONORABLE MENTION

Saint Joseph Hospital
Denver, Colo.

BUILDING TEAM
Submitting firm: Mortenson Construction (CM/GC)
Owner: SCL Health
Architect: ESJH Design Team (joint venture of Davis Partnership, H+L Architecture, and ZGF Architects)
Interior architect: H+L Architecture
Structural/civil engineer: Martin/Martin
MEP engineer: Cator, Ruma & Associates

GENERAL INFORMATION
Project size: 831,327 sf
Construction cost: $360 million; total cost: $623 million
Construction time: December 2011 to July 2014
Delivery method: CM at risk

Related Stories

| Aug 29, 2022

Montana becomes first U.S. state to approve 3D printing in construction

Montana is the first U.S. state to give broad regulatory approval for 3D printing in building construction.

Architects | Apr 22, 2022

Top 10 green building projects for 2022

The American Institute of Architects' Committee on the Environment (COTE) has announced its COTE Top Ten Awards for significant achievements in advancing climate action.

Concrete Technology | Apr 19, 2022

SGH’s Applied Science & Research Center achieves ISO 17025 accreditation for concrete testing procedures

Simpson Gumpertz & Heger’s (SGH) Applied Science & Research Center recently received ISO/IEC17025 accreditation from the American Association for Laboratory Accreditation (A2LA) for several concrete testing methods.

2021 Building Team Awards | Jan 14, 2022

First public-private partnership project in Veterans Administration history saves $34 million in costs

LEO A DALY and McCarthy Building Companies head the project team for the Omaha VA Ambulatory Care Center in BD+C’s 2021 Building Team Awards.

Building Team Awards | Dec 8, 2021

A performing arts center celebrates a legendary rocker and his birthplace

Buddy Holly Hall in Texas receives BD+C’s Silver Building Team Award.

Building Team Awards | Dec 7, 2021

A rapid response to a health emergency

Baptist Hospital of Miami’s 233-bed Hope Tower receives BD+C’s Bronze Building Team Award

Building Team Awards | Dec 3, 2021

Putting science on display, thanks to a design-build approach

UC Riverside’s Plant Growth Environments Facility receives BD+C’s Bronze Building Team Award.

Building Team Awards | Dec 2, 2021

An academic ‘precinct’ brings arts and sciences together

Wofford College’s Chandler Center for Environmental Studies receives BD+C’s Silver Building Team Award.

Building Team Awards | Dec 1, 2021

Denver sets the bar for water reclamation and reuse

A new administration building for the city’s water utility company scores Platinum in BD+C’s 2021 Building Team Awards.

2021 Building Team Awards | Nov 17, 2021

Caltech's new neuroscience building unites scientists, engineers to master the human brain

The Tianqiao and Chrissy Chen Institute for Neuroscience at the California Institute of Technology in Pasadena wins a Gold Award in BD+C's 2021 Building Team Awards.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021