Building a Double Wall

The new outer envelope of the A.J. Celebrezze Federal Building serves as a therm
The new outer envelope of the A.J. Celebrezze Federal Building serves as a thermal blanket in winter, reducing the need for mechanical heat; in summer, heat gain in the cavity between old and new walls does not transfer inside.

The A.J. Celebrezze Federal Building, a 32-story office building in Cleveland, Ohio, was built in the late 1960s for the U.S. General Services Administration. As with many early generation window walls, significant deterioration has occurred over time due to moisture damage from failed drainage systems. This resulted in delamination of exterior wall panels, compromising the air and moisture barrier. The panels had been stabilized with a retrofit, but their effectiveness as a perimeter barrier has reached its limit, as evidenced by the occurrence of frost inside the exterior envelope during winter.

Our firm, Interactive Design, was engaged as the architect to correct the façade deficiencies for the $121 million project, which is funded under the American Recovery and Reinvestment Act of 2009. To mitigate these issues the façade renovation program was focused on four primary requirements: 1) repair/replacement of the building envelope, 2) providing blast protection, 3) upgrading the energy conservation of the envelope, and 4) maintaining full occupancy during construction.

Blast pressure analysis indicated that the frame of the building would accommodate increased loads, but only at the column floor beam connections. Noncomposite slab construction eliminated the transfer of loads via diaphragm. Therefore, new tube beams were added externally to transfer the wind, blast, and gravity loads to these points. Deflection of the tubes under blast conditions may not impact the structural frame. The geometry formulated an exterior configuration two feet, six inches deep, which led logically to the investigation of a double wall assembly.

Originally the project was conceived as an overclad wall system. However, adding an overclad assembly would have extended the volume of interior spaces, resulting in significant fire protection modifications and perimeter air distribution modifications to the existing fan coil units.

MAKING DOUBLE WALL VIABLE
Double wall technology is one of the most complex building envelope forms. Originally developed and employed in Europe, it has been relatively slow in migrating to the U.S. However, higher energy costs are now making these systems more viable. In new construction, the inability to offset the initial high envelope costs through energy savings historically has been the obstacle for double wall usage. Specialized projects, such as museum construction, can justify these initial costs due to constant temperature/humidity requirements. For renovation projects such as the A.J. Celebrezze Federal Building, the existing interior wall can be reused as the interior skin to offset much of the cost delta.

The design process for double walls relies on the integration of all systems. The ventilation environment of the building informs the design. It is imperative that an accurate and robust energy model be developed to assist in the analysis and creation of the double wall. A fundamental challenge was to understand the effect of a double wall upon the existing building. The design team embarked upon an extensive series of computational fluid dynamic studies. Winter, spring/fall, and summer conditions were run in extreme temperature and solar conditions. The purpose of the CFD analysis was to fully understand the temperature relationships in the wall cavity and occupied spaces during seasonal variances.

The architects were able to manipulate glazing layups, light shades, and frit variations to impact the performance characteristics. The design team pursued a variety of critical design paths simultaneously. These included both actively ventilated and sealed cavity conditions.

A significant factor for this project is that the building has historically a very low winter relative humidity. This ultimately permitted a sealed cavity system with no ventilation from either the inside or outside. The temperature and humidity of the internal cavity are allowed to float, so to speak, with its surrounding environments. It acts as a buffer between inside and outside, mitigating the differences between the two without using additional mechanical means, and minimizing energy consumption.

CUTTING ENERGY USE 65%
This system is designed to improve the existing perimeter energy consumption by approximately 65%. It is most efficient to the building during the winter months, when it acts like a thermal blanket and significantly reduces the need for heat from the existing perimeter fan coils. During summer months, shading systems block direct solar gain to the tenant-occupied spaces. The cavity will increase in temperature while not detrimentally affecting the interior environment or the existing mechanical system.

The final configuration is a noncombustible, sealed assembly that requires minimal maintenance. Access to the cavity is provided at each floor by operable interior windows in the inner wall.

The passive double wall system being employed at the A.J. Celebrezze Federal Building is one solution to the growing number of fully occupied buildings that have aging or seriously deteriorated skins. Economic constraints dictate that building owners cannot afford to empty their buildings of tenants to do replacement or maintenance work on façades. Therefore, systems such as this may offer an alternative to complete façade replacement, at the same time lowering energy consumption and enhancing sustainability by preserving existing materials. BD+C
--
Charles Young is a partner with Interactive Design, Inc., an architecture firm based in Chicago. This article is adapted from Chicago Architect, the journal of AIA Chicago.

         
 

Comments on: "Building a Double Wall"

The colorful ribboned flooring at Toronto’s Corus Quay mimics the iconic corkscr
The colorful ribboned flooring at Toronto’s Corus Quay mimics the iconic corkscr
Discussions of commercial flooring tend to focus on the floor covering or finish material. This is hardly surprising, since the covering is the part of the floor that stakeholders see, interact with, and care about most. The...
The use of light load-bearing glass to create transparent stairs, floors, and ot
The use of light load-bearing glass to create transparent stairs, floors, and ot
Glass has taken on new life in recent building years. Long valued for its transparency and lightness, glass is now also being considered for its structural and protective capabilities. Beyond the technique known as...
Building owners must plan ahead for roof replacement to avoid emergency leak rem
Building owners must plan ahead for roof replacement to avoid emergency leak rem
No building owner wants to be caught unprepared by catastrophic roof failure. Emergency roof replacements tend to be more expensive than planned ones, and damage to interiors may mean unrecovered costs and detrimental...
AIA: New Developments in Concrete Construction
AIA: New Developments in Concrete Construction
Concrete has long been a reliable building material for commercial and institutional projects. Yet recent trends, including the growth in hospitality and urban rental project starts, as well as mixed-use towers and transit-...
AIA Rainscreens BD+C DEcember 2011
AIA Rainscreens BD+C DEcember 2011
Until recently, it has been lighting, mechanical, and control system upgrades which have received the most attention in the green building movement. At long last, the industry is now recognizing building enclosures as a long...
Brick and stone masonry have served as reliable and valuable elements of commercial building projects for centuries, gracing urban and rural landscapes since time immemorial. Building Teams have trusted clay brick to bring...
Making the Most of the Reconstruction Boom Reconstruction in its many forms—tenant improvements, retail fitouts, adaptive reuse, historic preservation, gut rehab, and so on—is keeping many design and construction firms...
The topic of water shortages is nothing new, as cities around the globe struggle with drought, water quality, supply constraints, and failing infrastructures. However, the idea of new plumbing codes and design standards...
Guard booths, stations and shelters are defense strategy linchpins, becoming increasingly integral to perimeter defense planning. Before evaluating the efficacy of different guard booth configurations, and before selecting a...
From the company that brought you Construction Computing Magazine’s 2011 BIM Product of the Year ArchiCAD 15, the “Get There Faster with ArchiCAD” whitepaper examines five critical areas to explore before making your final...
Download Complete White Paper Download Introduction Download Chapters 1-4Defining Net-Zero Energy Buildings
Our seventh White Paper on Green Buildings focuses on the role of water in sustainable design and construction. The editors conclude with a set of 21 detailed recommendations for the consideration of the Building Teams, home...