Modular fire station allows for possible future reconfigurations

Modular Building

Modular fire station allows for possible future reconfigurations

Rancho Mission Viejo’s Fire Station 67 deployed offsite fabrication and rapid onsite assembly, resulting in a construction timeline of six months.


By Novid Parsi, Contributing Editor | February 6, 2024
Modular fire station, Rancho Mission Viejo’s Fire Station 67
Fire Station 67, Rancho Mission Viejo, Calif. Photo © Nic Lehoux, courtesy Wittman Estes

In Southern California’s Rancho Mission Viejo (RMV), Fire Station 67 has been designed and constructed as a prefab, modular build—enabling faster completion and future reconfiguration.

Designed by Seattle-based Wittman Estes, the 4,667-sf station was prefabricated offsite as 10 modules that were then assembled onsite. The offsite fabrication and rapid assembly led to a streamlined design, documentation, and permitting process. This approach allowed for parallel site development work in California and factory construction in Nevada, resulting in a construction timeline of six months. 

Fire Station 67: Modular System

The modular system also allows for relocation and reconfiguration. The sturdy, durable steel modules can be easily transported and rearranged for possible future uses, such as an environmental learning center for RMV.

Modular fire station, Rancho Mission Viejo’s Fire Station 67
Fire Station 67. Photo © Nic Lehoux, courtesy Wittman Estes

Fire Station 67 includes a vehicle bay for two fire trucks, six sleeping rooms, a day room, kitchen/dining room, dispatch/workspace, and a captain’s office. The 12-foot modules were assembled around a shaded, semi-protected central courtyard.

Construction Strategy

The building configuration enables the firefighters to serve the public quickly while also feeling calm and privacy. The north-facing public entry, captain’s office, and dispatch room face the neighborhood. The more active areas, including break room, kitchen, and fitness rooms, face east toward the firetrucks. And the sleeping rooms and bathrooms are located in a quiet zone in the west. The firetruck bay is painted bright red, while the interior spaces have a neutral, tranquil palette.

Modular construction plan of fire department

In response to climate change and the rising risk of wildfires, the prefab structure is clad in fireproof, corrugated steel siding. To improve indoor air quality, Wittman Estes designed an open-air apparatus bay to bring in fresh outside air and eliminate the need for large exhaust machines.

On the Building Team:
Clients: Orange County Fire Authority and Rancho Mission Viejo
Architect: Wittman Estes
Interior designer: Birsel+Seck
Structural engineer: DCI Engineers
Landscape architect: Land Concern
Civil engineer: Fuscoe Engineering
GC: Xtreme Cubes 

Modular fire station, Rancho Mission Viejo’s Fire Station 67
Photo © Nic Lehoux, courtesy Wittman Estes
Rancho Mission Viejo’s Fire Station 67
Photo © Nic Lehoux, courtesy Wittman Estes

Related Stories

Sponsored | Modular Building | Mar 30, 2015

Spring cleaning tips for modular space

Modular structure manufacturer Williams Scotsman shares seven things to do to prep modular units for the spring.

Multifamily Housing | Mar 18, 2015

Prefabricated skycubes proposed with 'elastic' living apartments inside

The interiors for each unit are designed using an elastic living concept, where different spaces are created by sliding on tracks.

Sponsored | Modular Building | Mar 16, 2015

Modular Space Showcase: Helping BP take command in the Gulf of Mexico

Immediate emergency response to minimize and remedy environmental damage called for temporary, modular spaces.

Modular Building | Mar 10, 2015

Must see: 57-story modular skyscraper was completed in 19 days

After erecting the mega prefab tower in Changsha, China, modular builder BSB stated, “three floors in a day is China’s new normal.”

Sponsored | Modular Building | Mar 9, 2015

Drilling Deeper: Eagle Ford Shale moving up despite oil prices going down

Like many other energy hotbends throughout the continent, demand for modular structures isn't decreasing with oil prices

Sponsored | Modular Building | Mar 3, 2015

Modular construction brings affordable housing to many New Yorkers

After city officials waived certain zoning and density regulations, modular microunits smaller than 400 square feet are springing up in New York.

K-12 Schools | Feb 25, 2015

Polish architect designs modular ‘kids city’ kindergarten using shipping container frames

Forget the retrofit of a shipping container into a building for one moment. Designboom showcases the plans of Polish architect Adam Wiercinski to use just the recycled frames of containers to construct a “kids city.”

Modular Building | Feb 23, 2015

Edge construction: The future of modular

Can innovative project delivery methods, namely modular construction, bring down costs and offer a solution for housing in urban markets? FXFOWLE’s David Wallance discusses the possibilities for modular.

Sponsored | Modular Building | Feb 23, 2015

Modular Space Showcase: Sales center brings curb appeal

The Welcome Center received rave reviews from the customer as well as community residents and potential buyers.

Sponsored | Modular Building | Feb 17, 2015

When lava flow in Hawaii threatens a public school district, officials turn to modular

Hawaii Modular Space, a Williams Scotsman company, designed temporary classroom space for the Pahoa and Keeau schools that would become displaced due to ongoing lava flow in Pahoa, Hawaii.

boombox1
boombox2
native1

More In Category

Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021