The 173-acre TechnipFMC John T. Gremp Campus is the first element in north Houston’s Generation Park planned community. The 1.7 million-sf complex was completed in March 2016. Two months later, FMC Technologies and European oil and gas equipment technology company Technip formally announced their merger.
The new campus consolidates manufacturing, offices, and amenities for thousands of employees who were spread across six locations in the Houston area.
The Building Team, led by design giant Gensler, developer Trammell Crow, and contractor D.E. Harvey Builders, successfully dealt with requests from the owner after work had already begun.
First, TechnipFMC wanted to change two primary office buildings that were connected at only one level into a single building that would be connected on all levels. The project team used 3D visualization for fast design approval to insert a multi-level vertical connector into shared amenity space on each level.
Next, the owner added a new sophisticated process equipment product line to the project scope very late in the design process. The Building Team created a new design that allowed for placement of an in-ground rail system, underground utility distribution system, and automated welding machine system; all this, after most of the structure was already built.
TechnipFMC then announced that it was developing a new subsea equipment system that was significantly larger and heavier than the original building was designed for. The Building Team modified floor thicknesses, added 50 tons to the crane capacity, revised equipment circulation, and increased the size of the testing area without affecting foundation pours that were already in progress.
The Technip FMC campus in north Houston is marked by a 369,000-sf LEED Gold office building. The 2,036-space parking garage gives priority space to fuel-efficient vehicles. Landscape irrigation uses non-potable water. Photo: Ryan Gobuty/Gensler.
Building Team – Submitting firm, architect, interior architect Gensler Developer Trammell Crow Co. Structural engineer Cardno Haynes Whaley Mechanical engineer Wylie Consulting Engineers Contractor D.E. Harvey Builders
General Information – Size 1.7 million sf Construction cost Confidential Construction period April 2014 to March 2016 Delivery method Design-bid-build
Related Stories
Architects | Jan 18, 2016
EHDD’s Monterey Bay Aquarium wins AIA Twenty-five Year Award
The aquarium set new technical standards for the building type, which still influence today, such as the flow-through seawater-based heat pump system, naturalistic exhibitions, and corrosion protection.
Building Team Awards | Apr 10, 2015
14 projects that push AEC teaming to the limits
From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.
Building Team Awards | Apr 10, 2015
Prefab saves the day for Denver hospital
Mortenson Construction and its partners completed the 831,000-sf, $623 million Saint Joseph Hospital well before the January 1, 2015, deadline, thanks largely to their extensive use of offsite prefabrication.
Building Team Awards | Apr 10, 2015
Anaheim’s soaring intermodal hub
Anaheim's Regional Transportations Intermodal Center is the largest ETFE project in North America.
Building Team Awards | Apr 10, 2015
Virtual collaboration helps complete a hospital in 24 months
PinnacleHealth needed a new hospital STAT! This team delivered it in two years, start to finish.
Building Team Awards | Apr 10, 2015
New arts venue reinvigorates Virginia Tech's campus
The STV-led Building Team creates a world-class performance and arts venue with learning and entrepreneurial dimensions.
Building Team Awards | Apr 9, 2015
Multifaced fitness center becomes campus landmark
A sloped running track and open-concept design put this Building Team to the test.
Building Team Awards | Apr 9, 2015
Nation's first LEED-certified bus depot
A bus garage in Harlem shows that even the most mundane of facilities can strut its environmentally sensitive stuff.
Building Team Awards | Apr 9, 2015
Setting the bar for port-of-entry design
Whenever you eat a tomato from Mexico, there’s a one-in-three chance it came through this LEED Gold gateway.
Building Team Awards | Apr 9, 2015
Big D’s billion-dollar baby: New Parkland Hospital Tops the Chart | BD+C
Dallas’s new $1.27 billion public hospital preserves an important civic anchor, Texas-style.