The 173-acre TechnipFMC John T. Gremp Campus is the first element in north Houston’s Generation Park planned community. The 1.7 million-sf complex was completed in March 2016. Two months later, FMC Technologies and European oil and gas equipment technology company Technip formally announced their merger.
The new campus consolidates manufacturing, offices, and amenities for thousands of employees who were spread across six locations in the Houston area.
The Building Team, led by design giant Gensler, developer Trammell Crow, and contractor D.E. Harvey Builders, successfully dealt with requests from the owner after work had already begun.
First, TechnipFMC wanted to change two primary office buildings that were connected at only one level into a single building that would be connected on all levels. The project team used 3D visualization for fast design approval to insert a multi-level vertical connector into shared amenity space on each level.
Next, the owner added a new sophisticated process equipment product line to the project scope very late in the design process. The Building Team created a new design that allowed for placement of an in-ground rail system, underground utility distribution system, and automated welding machine system; all this, after most of the structure was already built.
TechnipFMC then announced that it was developing a new subsea equipment system that was significantly larger and heavier than the original building was designed for. The Building Team modified floor thicknesses, added 50 tons to the crane capacity, revised equipment circulation, and increased the size of the testing area without affecting foundation pours that were already in progress.
The Technip FMC campus in north Houston is marked by a 369,000-sf LEED Gold office building. The 2,036-space parking garage gives priority space to fuel-efficient vehicles. Landscape irrigation uses non-potable water. Photo: Ryan Gobuty/Gensler.
Building Team – Submitting firm, architect, interior architect Gensler Developer Trammell Crow Co. Structural engineer Cardno Haynes Whaley Mechanical engineer Wylie Consulting Engineers Contractor D.E. Harvey Builders
General Information – Size 1.7 million sf Construction cost Confidential Construction period April 2014 to March 2016 Delivery method Design-bid-build
Related Stories
Giants 400 | Aug 11, 2021
BD+C Awards Programs
Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400
Building Team Awards | Mar 12, 2021
2021 Building Team Awards Entry Information
Only new construction projects completed on or after January 1, 2020 are eligible. Deadline for submissions: May 14, 2021.
Building Team Awards | Mar 12, 2021
Deadline extended for the 2021 Building Team Awards
BD+C's Building Team Awards is the industry's only recognition program to honor projects that achieve excellence in both design/construction and collaboration of the AEC/O team. Deadline for entries: May 14, 2021.
Building Team Awards | Nov 4, 2020
12 projects earn BD+C's 2020 Building Team Awards
The Statue of Liberty Museum, Allianz Field, and the Long Beach Civic Center are three of the projects awarded with BD+C's 2020 Building Team Awards.
Building Team Awards | Nov 3, 2020
Birmingham's haven for the homeless
A coalition of ministries raised millions to build a new home for homeless men in Alabama’s largest city. The Firehouse Shelter wins Honorable Mention in the 2020 Building Team Awards.
Building Team Awards | Nov 2, 2020
It's back to the future for this contractor
Poettker Construction’s new headquarters in rural Breese, Ill., is recognized with a Bronze Award in BD+C’s 2020 Building Team Awards.
Building Team Awards | Nov 2, 2020
Long Beach gets a municipal marvel
The Long Beach Civic Center is honored with a Bronze Award in the 2020 Building Team Awards.