Oklahoma’s first modular hotel will begin construction next month

Modular Building

Oklahoma’s first modular hotel will begin construction next month

Guerdon Modular Buildings will produce 81 modules for this project. 


By John Caulfield, Senior Editor | May 17, 2016

The AC Hotel in a neighborhood in Oklahoma City will be Oklahoma's first modular-built hotel, as well as the first for its developer. Image: Courtesy Guerdon Modular Buildings 

NewcrestImage, a privately owned, Lewisville, Texas-based hotel development, construction, and management firm, plans to build the first hotel in Oklahoma to use modular construction technology.

The 142-room AC Hotel Bricktown, in Oklahoma City, will also be NewcrestImage’s first modular hotel. The developer has entered into a partnership with the manufacturer Guerdon Modular Buildings to produce the modules for this project.

ADG Inc. is the architect of record, and Duncan Miller Ullmann the interior designer of the five-story hotel. Metul Patel, NewcrestImage’s Chairman and CEO, describes the hotel’s accommodations as “European-inspired.”

The first floor will be built using traditional construction. The upper four floors will be built from 81 modules provided by Guerdon’s factory in Boise, Idaho. Modular production is scheduled to begin next month, and the finished modules are scheduled to be shipped, via flatbed trucks, over four days in October.

All rooms and finishes will follow AC Hotel specifications upon delivery, and be indistinguishable from the Marriott brand’s other hotels.

The hotel, which is scheduled to open in June 2017, and which NewcrestImage will own and operate, will be located next to the 13,000-seat Chicksaw Bricktown ballpark and within a few blocks of the Cox Convention Center.

(NewcrestImage is deploying conventional construction to build another hotel in the Bricktown neighborhood, this one a 135-room Hyatt Place, which will be adjacent to OKC’s Central Business District. It’s scheduled to open in late 2017.)

“Our goal has been to integrate closely with NewcrestImage in order to make every aspect of the construction process flawless and worry-free—everything from the design and build to mapping out the delivery and installation process,” said Lad Dawson, Guerdon’s CEO.

Earlier this year, BD+C quoted Dawson as stating that Guerdon had entered into an agreement to help “a large hotel chain” (Marriott, according to one knowledgeable source) build 1,000 modular hotel rooms per year. He did not provide specifics or timetables. But that same article quoted The Modular Building Institute and STR that more modular hotel construction in the U.S. is needed for hoteliers to keep up with rising demand from guests.

Related Stories

Building Materials | Jan 9, 2017

Architects and researchers are developing new techniques for building in space

As setting foot on Mars becomes a more realistic goal, the search for how to best develop Architecture for the Red Planet is heating up.

Modular Building | Jul 22, 2016

PNC Bank’s 'Tiny Branch' opens on West Virginia University campus

The new branch doesn’t need much space for its ATM and new accounts and personal loans services.

Transit Facilities | Jun 12, 2016

Philippines’ oldest city getting its first public bus system

New York-based CAZA designed the modular bus stops with the city’s extreme weather conditions in mind.

Modular Building | Feb 26, 2016

CHPS releases new program, first model for prefab modular classrooms

Provides standards for indoor air quality, energy efficiency, materials, and waste management.

Game Changers | Feb 5, 2016

Asia’s modular miracle

A prefab construction company in China built a 57-story tower in 19 days. Here’s how they did it.  

Game Changers | Feb 4, 2016

GAME CHANGERS: 6 projects that rewrite the rules of commercial design and construction

BD+C’s inaugural Game Changers report highlights today’s pacesetting projects, from a prefab high-rise in China to a breakthrough research lab in the Midwest.

Modular Building | Feb 1, 2016

Hotel developers turn to modular construction to meet demand

A $90 million rebuilding project in Yellowstone National Park exemplifies this trend.

| Jan 14, 2016

How to succeed with EIFS: exterior insulation and finish systems

This AIA CES Discovery course discusses the six elements of an EIFS wall assembly; common EIFS failures and how to prevent them; and EIFS and sustainability.

Modular Building | Dec 13, 2015

Undaunted, Forest City pushes ahead on modular construction

The president of its FC Modular division says new projects are under consideration, even as competitors falter or fall by the wayside. 

Greenbuild Report | Dec 1, 2015

Data centers turn to alternative power sources, new heat controls and UPS systems

Data centers account for 2% of the nation’s electricity consumption and about 30% of the power used annually by the economy’s information and communications technology sector, according to the National Renewable Energy Laboratory.

boombox1 - default
boombox2 -
native1 -

More In Category




Modular Building

Building with shipping containers not as eco-friendly as it seems

With millions of shipping containers lying empty at ports around the world, it may seem like repurposing them to construct buildings would be a clear environmental winner. The reality of building with shipping containers is complicated, though, and in many cases isn’t a net-positive for the environment, critics charge, according to a report by NPR's Chloe Veltman.

halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021