flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Topcon Automated Trimmer Speeds Grade Prep

Topcon Automated Trimmer Speeds Grade Prep

T.J. Lambrecht Construction outfitted their GOMACO road base trimmer with GPS controls.


By By Daniel C. Brown | August 11, 2010

Building a new highway by conventional methods is a laborious process. Getting a perfect grade often involves base stabilization, multiple passes with a motor grader, extensive compaction, and some kind of trimming.

But on a Texas tollway project near Austin, the process of preparing the grade is being cut short with a world's first — a GPS-equipped road base trimmer that automatically steers itself, cuts grade to within one-quarter inch, and takes the place of two motor graders, says the contractor.

SH 45SE Joint Venture

The SH 45SE Turnpike will link I-35 at FM 1327, north of Buda, TX, to the junction of SH 130 and US 183 near Mustang Ridge east of Austin Bergstrom International Airport. The 7.4-mile-long facility will be constructed as a four-lane roadway with controlled access and a wide center median. Grade-separated interchanges at Interstate 35, North Turnersville Road, FM 1625, and State Highway 130/US 183 are included in the "Interim" construction.

The total $139.7-million TxDOT project is a joint venture contract held by Balfour Beatty Infrastructure, Inc./T.J. Lambrecht Construction, Inc. Lambrecht's portion involves 1.9 million cubic yards of embankment, 2.1 million cubic yards of excavation, and various culverts and drainage works.

Balfour Beatty is doing the paving and bridge construction on the project. Construction began early last July and is scheduled for completion by May 1, 2009.

A Perfect Grade

The trimmer can produce the same amount of finished grade as two GPS motor graders working together, according to Mike Wehling.

T.J. Lambrecht Construction is cutting the road's subgrade and base with a GOMACO 9500 trimmer equipped with a Topcon Millimeter Global Positioning System (GPS). Cutting a pass 16 feet, 8 inches wide, the big trimmer is used at three stages of subgrade and base construction, explains Mike Wehling, Lambrecht's regional survey/GPS machine control manager. The contractor first employs an all-Caterpillar fleet of dozers and scrapers to bring the grade to within 2/10 of a foot. Two of the dozers are equipped with GPS systems.

Next the trimmer swings into action. It cuts grade with a rotating drum fitted with teeth. With the aid of the Topcon Millimeter GPS system, the trimmer brings the grade to within one-quarter inch. Then a Caterpillar RM 500 stabilizer mixes lime into the subgrade 6 inches deep. The grade is rolled with a pneumatic compactor and cured for four days, according to Wehling. Another phase of remixing and compaction follows curing.

"Then we run the trimmer on it again, for a second time, and get it to within one-quarter inch," says Wehling. "Next we bring in 30 inches of select fill material, rough-grade that with the GPS dozers, and compact it again. The trimmer makes a final pass, once again bringing the grade to within one-quarter inch. That is followed by a tack coat, a 4-inch hot mix asphalt base, and 12 inches of concrete pavement."

"The trimmer can produce the same amount of finished grade as two GPS motor graders working together," says Wehling. "The trimmer makes one pass and the grade is perfect, but with motor graders you have to make multiple passes. The trimmer needs to cut about 2/10 of a foot to keep the proper head of material in front of it. At that depth it can do up to 40 feet per minute under ideal conditions. If it has to cut more than 4/10 or 5/10 foot, we have to slow it down too much.

"We had the first two trimmers in the world equipped with Topcon Millimeter GPS," says Wehling. "The GPS is used to control steering, and the Millimeter laser is used to control grade. At about 600-foot intervals down the road, we set up the fan-beam laser on control points. The trimmer uses two of them, and we leapfrog them one after the other down the road. The laser transmits a fan-shaped beam to the two receivers on the trimmer, one on each side."

The Millimeter system works much like a regular Topcon GPS system. Lambrecht loads three elements — a 3-D model of the design, a localization file and a linework file — into the control box on the trimmer. The localization file fits the design to control points on the site, and the linework file controls horizontal positioning.

The Topcon Millimeter GPS system cost about $100,000, Wehling said. That buys two lasers and two receivers plus the control box and receiver/computer that mount on the machine. But, says Wehling, consider that very little surveying — and no stringline — is necessary. If you compare GPS to the cost of a three-man survey crew and a four-man stringline crew, he says, you would go through $100,000 in pretty quick order.

"We wouldn't even own the trimmer without Millimeter GPS," says Wehling. "It would be too costly to run the trimmer with stringline. Instead we would have to run two motor graders with GPS systems to equal the production of the trimmer."

Lambrecht is also using Topcon Millimeter GPS systems on two Cat 14M motor graders at the S.H. 45 project for the Texas DOT. "We use the graders for places we can't get into with the tracked trimmer," says Wehling. In addition, Lambrecht has fitted a Caterpillar D6T with a Topcon GPS system for cutting slopes and ditches.

Lambrecht was an early adapter of GPS systems. Six years ago, the contractor bought a Topcon robotic total station and used it with a Caterpillar 14H motor grader. "We bought the GTS 2000 total station, sold our trimmer, and haven't set a stringline since," he says.

boombox1 - default
boombox2 -
native1 -
halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021