flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Sacramento State Upgrades Sewer System With "Green" Design

Sacramento State Upgrades Sewer System With "Green" Design

Retrofitting an existing infrastructure with an environmentally friendly system can be challenging and demanding


By By James McRay, Efficiency Production, Inc.; and Bruce Ellis, D.P. Nicoli, Inc. | August 11, 2010

California State University — Sacramento (Sacramento State) is "going green." They have several new building projects under way which are incorporating aspects of "green building," a process to create buildings and supporting infrastructure that minimize the use of resources, reduce harmful effects on the environment, and create healthier environments for people.

One of the green building projects at Sacramento State includes upgrading the sewer system on campus. A new 33,000-gallon holding tank and pump station were recently installed to augment the current system. Tidelands Construction Company from Brentwood, California, was the general contractor installing the tank and pump station.

On a busy campus such as Sacramento State, a project such as this was not going to be easy or routine. The excavation site had very limited access and many surrounding obstacles to contend with, including:

A main road for the university and an adjacent parking structureA drainage ditch and railroad line in close proximity on the opposite side of the excavation from the roadAn existing pump station and generator near the excavation siteHigh volume of both vehicle and pedestrian traffic on the adjacent road

There was little to no room for equipment access except from the ends of the long, deep and narrow excavation, unless the road was closed. Shoring the pit was a major challenge as traditional sheet piling or sloping was not an option.

D.P. Nicoli, Inc. was contacted to help solve the shoring problem. Ryan Jaffe, V.P. of Slide Rail Shoring, worked with Phil Toelkes, owner of Tidelands Constructions, and J. M. Turner Engineering to come up with a shoring plan that would work for the unique and challenging situation, yet still be affordable and relatively easy for the contractor to install.

D.P. Nicoli consulted with Mike West, vice president of Engineering at Efficiency Production, Inc. — the country's leading manufacturer of trench shielding and shoring equipment. D.P. Nicoli proposed utilizing Efficiency's Slide Rail System in a six-bay, 4-Sided Multi-Bay Configuration. Nicoli's experience with large pits using Efficiency's slide rail and the patented waler system seemed like a good fit.

"Efficiency's Slide Rail really was the perfect solution," says Hans Vermeulen, project engineer with Turner Engineering. "Everything went according to how it was drawn up."

"I'd worked with Nicoli for other shoring needs, but never for the Efficiency Slide Rail," says Tony Zottola, project superintendent for Tidelands Construction. "Installation went really sweet all the way to the bottom without any binding or twisting. With other slide rail systems I've used, I've needed to get into the hole and weld the system just to hold it together so it wouldn't fall apart," Zottola added.

"Dig and Push" system reduces over-excavation

Efficiency's Universal Slide Rail is a component shoring system comprised of steel panels (similar to trench shield sidewalls) and vertical steel posts. The versatile system can be used in a variety of configurations, such as small four-sided pits; large unobstructed working pits as big as 50 feet by 50 feet with Efficiency's ClearSpan™ System; or in a linear Multi-Bay configuration to install length of pipe over 40 feet.

Slide Rail is installed simultaneously as the trench or pit is excavated by sliding the panels into integrated rails on the posts — either double or triple rails depending on needed depth — then pushing the panels and posts incrementally down to grade as the pit is dug; a process commonly referred to as a "dig and push" system.

Big clearance for tank made easy with Efficiency Slide Rail

The entire excavation needed to be 16 feet wide and 89 feet long. The tank was 64 feet long and needed to be placed in a single pick set at 28 feet deep.

The biggest challenge was engineering a shoring system that would provide an unobstructed open clearance to the pit of at least 60 feet. That is where Efficiency's Slide Rail System provides an advantage over other manufacturer's slide rail. Efficiency's multi-bay configuration uses parallel beams that incorporate into the vertical posts and pin-in-place standard trench box spreaders as cross-members. The parallel beams have rollers, and when horizontal walers and sacrificial members are utilized, the entire cross-member apparatus can be easily removed resulting in an unobstructed clearance to the shored excavation.

"The Efficiency slide rail has a little more room to play with because of the integrated rails on the posts and the moveable parallel beams sliding along the face of the posts," Zottola added. "This was very beneficial due to the limited access that we had. We could only install from a couple of spots around the pit, but we had no problem handling the system's components."

Slide Rail is installed and removed incrementally, which allows the trench to be properly shored throughout the entire installation or removal process, maximizing the stability of the surrounding ground. "Clearly, we had no safety issues with the system; it was very safe," said Zottola.

The system was engineered to incorporate a 60-foot-long W24x162 I-beam welded onto a larger W36x300 I-beam waler, which was then welded to the outside of the vertical posts at the top. Sacrificial beams were placed at the shoes of the linear posts below grade, to eliminate the potential of deflection when the cross-member assembly was removed. D.P. Nicoli, Inc. supplied all the slide rail components and had their Senior Slide Rail Specialist Bruce Ellis on hand to work with the Tidelands crew.

Tank installation smooth and easy

Tidelands began the excavation by first benching and sloping down about 8 feet. The slide rail system components included four, 32-foot vertical corner posts and five sets of 32-foot linear posts; and 5-inch-thick, 14-foot-long, 8-foot and 4-foot tall slide rail panels. Tidelands used a Kobelco 400 excavator to install the system.

Water was encountered at 30 feet. A 6-inch pump was inserted and the water piped through a small sediment tank. A small Bobcat excavator was lowered into the pit to help finish the final grade.

The base and first section for the pump were set and backfilled at 28 feet deep. After the walers were secured to the posts and the sacrificial beams put in place, three of the five Efficiency parallel beam-spreader assemblies were removed for the tank set. The result was an unobstructed pit that was 60 feet long and was able to accommodate the 64-foot-long tank.

A crane was brought in to set the tank. The tank was also hooked up with a separate strap attached at one end to the excavator, which helped guide the nose of the tank under the last sets of spreaders. The tank was then sand-bagged in place and backfilled. Tidelands also used a CAT 375 excavator when removing the slide rail components.

The entire tank and lift station installation — from first cut to backfill — took about four weeks.

boombox1 - default
boombox2 -
native1 -
halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021