Georgia court limits contractors’ ability to foreclose on liens

The Georgia Court of Appeals ruled in 182 Tenth, LLC v. Manhattan Construction Company that lien claimants such as contractors, subcontractors, and materialmen, may not foreclose on a lien that includes unpaid general condition costs.

December 14, 2012 |

On private construction projects, contractors ordinarily have the right to file a mechanic's or materialman’s lien under applicable state law to collect unpaid sums due on a construction contract. However, on July 11, the Georgia Court of Appeals ruled in 182 Tenth, LLC v. Manhattan Construction Company that lien claimants such as contractors, subcontractors, and materialmen, may not foreclose on a lien that includes unpaid general condition costs.

These non-lienable costs may include: overhead, administrative, preconstruction, mobilization, phone/water, power, job site trailer, safety, and premiums for builder’s risk and general liability insurance.

Click here to learn more. +

 

Add new comment

Your Information
Your Comment

Filtered HTML

  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <blockquote> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

Plain text

  • No HTML tags allowed.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.
Refresh Type the characters you see in this picture. Type the characters you see in the picture; if you can't read them, submit the form and a new image will be generated. Not case sensitive.  Switch to audio verification.
Overlay Init