Georgia court limits contractors’ ability to foreclose on liens
The Georgia Court of Appeals ruled in 182 Tenth, LLC v. Manhattan Construction Company that lien claimants such as contractors, subcontractors, and materialmen, may not foreclose on a lien that includes unpaid general condition costs.
On private construction projects, contractors ordinarily have the right to file a mechanic's or materialman’s lien under applicable state law to collect unpaid sums due on a construction contract. However, on July 11, the Georgia Court of Appeals ruled in 182 Tenth, LLC v. Manhattan Construction Company that lien claimants such as contractors, subcontractors, and materialmen, may not foreclose on a lien that includes unpaid general condition costs.
These non-lienable costs may include: overhead, administrative, preconstruction, mobilization, phone/water, power, job site trailer, safety, and premiums for builder’s risk and general liability insurance.
Click here to learn more. +
More like this
- When do mechanic's lien rights expire?
- Broker doesn’t have to inform contractor that insurer went broke, California court rules
- Federal court reduces statute of limitations for OSHA action on record-keeping violations
- Courts struggle with the "economic loss rule"
- St. Paul cannot adopt overly restrictive egress windows policy, court rules