flexiblefullpage -
billboard - default
interstitial1 - interstitial
catfish1 - bottom
Currently Reading

Dam Rebuild With Roller-Compacted Concrete

Dam Rebuild With Roller-Compacted Concrete

AmerenUE determined that the safest and most economical method of rebuilding the Upper Reservoir would be to use an RCC design


By Staff | August 11, 2010

In the early hours of December 14, 2005, high atop Proffit Mountain in the Missouri Ozarks, a triangular section on the northwest side of the Taum Sauk Dam Upper Reservoir failed, discharging 1 billion gallons of water in 12 minutes. The failure sent a 20-foot crest of water down the Black River.

Image rendering courtesy of AmerenUE. Image rendering of what the Taum Sauk Dam Upper Reservoir will look like once rebuild is complete.

Not only was the Upper Reservoir itself destroyed, but neighboring areas also suffered. Fortunately, no deaths and very few injuries occurred in the destruction.

AmerenUE's Taum Sauk Plant was built in 1963 as a "pumped-storage" hydroelectric plant, storing water from the Black River in the Upper Reservoir and then releasing it to generate electricity when power was needed. The Upper Reservoir and hydroelectric plant are connected via a 7,000-foot tunnel that carries the water from the Black River to the Upper Reservoir.

In late winter 2007 AmerenUE started the rebuild of the dam's 189,486,001-cubic-foot Upper Reservoir, which requires 3 million cubic yards of concrete to be placed. Putzmeister's brand new Telebelt® TB 600 along with a Putzmeister TB 130 and 47Z-meter truck-mounted concrete boom pump are on site to help convey and place the concrete.

Image rendering courtesy of AmerenUE. Image rendering shows the rigourous design for Taum Sauk Dam's Upper Reservoir.

AmerenUE is a subsidiary of St. Louis-based Ameren Corporation, serving 2.3 million electric customers and 900,000 natural gas customers in a 64,000-square-mile area of Missouri and Illinois.Picking Teams

Ironton, Missouri-based Ozark Constructors, LLC — a joint venture of Pueblo West, Colorado-based ASI Constructors, Inc., and St. Louis-based Fred Weber, Inc. — was selected by AmerenUE as the team to rebuild Taum Sauk Dam's Upper Reservoir.

Paul Rizzo Associates, Inc., based in Pittsburgh, PA, was chosen as the Engineer of Record for the project and project manager for the rebuild.

"We are confident that the combination of ASI's knowledge and skill in dam construction, combined with Fred Weber's mining, aggregate processing and heavy civil construction expertise, is the perfect project team to successfully reconstruct the Taum Sauk Upper Reservoir Dam," says Thomas R. Voss, AmerenUE president and CEO. "AmerenUE would not consider returning this plant to service if company officials were not absolutely certain that the new design met, or exceeded, all safety criteria required by the Federal Energy Regulatory Commission (FERC). After much analysis, we are now confident that this plant can be returned to service and operated safely to restore a critical source of reliable power to our customers."

Why Roller-Compacted Concrete?

The rebuild calls for more than 3 million cubic yards of concrete, of which 2.7 million cubic yards is roller-compacted concrete (RCC) and will be used for the core of the dam.

"In order to comply with FERC rulings and working with Rizzo, AmerenUE determined that the safest and most economical method of rebuilding the Upper Reservoir would be to use an RCC design," explains Craig Giesmann, managing supervisor of hydro engineering for AmerenUE. "This design employs the latest in overflow structures, monitor and control systems, seismic design criteria and other safety features."

"Extensive testing was conducted prior to the start of the rebuild using the actual RCC mix components planned for the Taum Sauk Plant," adds Giesmann. "Rizzo is conducting tests and inspections throughout the rebuild to ensure the concrete mixes are consistently at the highest quality possible.

"In addition, the dam is designed to accommodate the most recent seismic design criteria and to withstand potential ground shaking from both near-field and far-field earthquake events up to a 2,500-year return period."

The dam is being built in nine sections that are being referred to as "Monolith No. 1" through "Monolith No. 9" consecutively, explains David Hall, project engineer for Ozark.

Although the majority of the dam will be RCC, according to Lee Schermerhorn, vice president of ASI and part of Ozark, the outer linings of the dam and various sections of the dam foundation, about 300,000 cubic yards, are made up of conventional concrete.

The conventional concrete is used for the dam lining, according to Giesmann, to provide a water barrier for the reservoir. In addition, according to Hall, the conventional concrete is also used to fill in holes in the natural rock of the foundation.

"Each monolith is 600 feet long and will reach 100 feet above the reservoir floor," adds Hall. "We start with the bare rock and begin building up from there with our equipment."

Hall says that after the rock holes are filled with conventional concrete, RCC is placed on top of that for the core of the dam in each Monolith.

Currently, Monolith No. 1 and No. 2 are being placed with the RCC mix and the foundation is being placed for Monolith No. 3, according to Hall.

On-Site Batching

Because the Taum Sauk Dam Upper Reservoir project required such a large amount of concrete, it was in Ozark's best interest to have on-site batch plants, according to Schermerhorn. Four batch plants are on site — three that hold the RCC mix and one that holds the conventional concrete mix.

"All four batch plants are running at the same time," Schermerhorn says. "About 10,000 to 12,000 cubic yards of concrete per day is generated by all four of the plants. The conventional batch plant mixes at 300 cubic yards per hour. The three RCC mix batch plants mix at three different rates; 250, 450 and 650 cubic yards per hour."

Getting from Point A to Point B

According to Schermerhorn, one of the biggest challenges on this project is getting the concrete where it needs to go.

"The devil is really in the details," notes Schermerhorn, "when it comes to delivering and placing the concrete from point A to point B with our equipment. The combination of the Upper Reservoir soaring 800 feet above the hydroelectric plant (a greater head than the Hoover Dam) and pumping and placing concrete into the 2.6 million square feet of formwork in the Upper Reservoir makes the terrain challenging to maneuver.

"To master the tricky job site, we've created a reliable method of delivering and placing concrete which requires our machines to work together to ensure the concrete gets to where it needs to go."

Integral to this material delivery system are three Putzmeister America, Inc. pieces of equipment: the Telebelt TB 600 telescopic belt conveyor, a TB 130 and a 47Z-meter truck-mounted concrete boom pump.

"The Telebelts convey and place the concrete into either loading trucks or into hoppers of other large-scale conveyors on site," comments Schermerhorn. "If loaded into a truck, the concrete is carried to where the large-scale conveyors are located. These machines then place the concrete where needed."

According to Schermerhorn, the TB 600 and TB 130 place both the RCC and conventional concrete, while the 47Z-meter places only the conventional concrete. Ozark has already placed more than 150,000 cubic yards total of RCC and conventional concrete combined for the Taum Sauk Dam Upper Reservoir rebuild.

The TB 600 is on its first project. Schermerhorn says, "The 24-inch width of the high-capacity main conveyor and feeder belts on the TB 600 is perfect for volume-intensive projects like the Taum Sauk Dam Upper Reservoir. The width absolutely provides the versatility this job needs.

"The TB 600 is designed to convey the harsh, zero-slump RCC mix," notes Schermerhorn. "There's no other way to convey a zero-slump RCC mix; you can't pump it, but we can convey it."

"The TB 600 features a rated output of 600 cubic yards per hour, which is an invaluable benefit for the project because of the massive amount of concrete we're placing and the multiple locations the machine is moved to on a daily basis," says Schermerhorn.

"Moving both Telebelts to multiple locations throughout the day is practically effortless. Simple teardown and quick setup is what Telebelts are known for," explains Schermerhorn. "The side panels of the standard folding hopper quickly fold into the feed conveyor and end panels connect with linchpins. The Telebelts' on-site efficiency is just incredible."

The TB 600's horizontal reach of 102 feet and the TB 130's horizontal reach of 126 feet 6 inches are a huge plus as well, according to Schermerhorn, especially accessing the difficult-to-reach areas in the Upper Reservoir to the loading trucks and conveyors.

According to Lee Arquette of Putzmeister Midwest Repair & Service Center (Midwest), in order for ASI's TB 130 to better convey and place the RCC mix, Midwest enhanced some of the structural elements and component configurations on ASI's TB 130 at its Milwaukee facilities per ASI's request.

"We made a number of modifications to ASI's TB 130 to get it ready for the Taum Sauk Dam Upper Reservoir project," notes Arquette. "We widened the exposed width of the main belt between the skirts, moved components or made special components to open transfer areas and enlarged some transfer components, which also received special processes and treatments. Some of these enhancements merited incorporation into new TB 130s currently in production and were definitely taken into consideration when the new Putzmeister TB 600 was designed."

The TB 130 can convey and place a variety of materials up to 4-inch aggregate.

In addition to the Telebelts, Schermerhorn says their Putzmeister 47Z-meter truck-mounted concrete boom pump is also assisting in helping to place the more than 3 million cubic yards of concrete for the rebuild.

"Our 47Z-meter is placing concrete in a method similar to our Telebelts into loading trucks or the large-scale conveyors," says Schermerhorn. "In addition, the 47Z has also helped to pump and place the conventional concrete needed to fill in the holes in the natural rock of the foundation for all of the Monoliths. Congested projects like this one are no match for the 47Z. With its compact outrigger footprint, its 151-foot-3-inch vertical reach and its 138-foot-1-inch horizontal reach, it overcomes day-to-day obstacles on site to help us get the concrete exactly where it's needed.

"The versatile five-section Z-Fold boom configuration on the 47Z handles space-restrictive areas and can pump even if the boom is not fully extended. It makes our operator's life so much easier," adds Schermerhorn.

The 47Z-meter boom pump can pump and place concrete up to 260 cubic yards per hour.

"Without the TB 600, TB 130 and 47Z-meter boom pump, this job would have been almost impossible," Schermerhorn says.

Ozark and its equipment will be on site through late 2009, when the Taum Sauk Dam Upper Reservoir is slated for completion.

"The fact that our company specializes exclusively in the construction and rehabilitation of dams, spillways and major water resource projects makes our involvement in this monumental project an unforgettable milestone in our history," remarks Schermerhorn.

 

Owner/Developer: AmerenUE — St. Louis, Missouri

Designer/Engineer: Paul Rizzo Associates, Inc. — Pittsburgh, Pennsylvania

General Contractor: Ozark Constructors, LLC, a joint venture of Fred Weber, Inc. (St. Louis, Missouri) and ASI Constructors, Inc. (Pueblo West, Colorado) — Ironton, Missouri

Equipment: One Putzmeister Telebelt TB 600, one Putzmeister Telebelt TB 130 telescopic belt conveyor, one Putzmeister 47Z-meter truck-mounted boom pump.
boombox1 - default
boombox2 -
native1 -
halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021