Construction milestone reached for $1B expansion of San Diego International Airport

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.

May 30, 2012 |
Bomel Construction Co. recently completed the structural concrete phase of the l

Calif.-based Bomel Construction Co. recently completed the structural concrete phase of the largest construction project ever undertaken at San Diego International Airport.

The $1 billion expansion, called Green Build, consists of a 430,000-sf. terminal building with 10 gates on the west side of Terminal 2 West, a dual-level roadway separating arriving and departing passengers, additional security lanes and an expanded concession area. The design-build project will be completed in the first quarter of 2013, with the new terminal opening soon thereafter.

Green Build, which includes a number of energy-saving and environmentally sensitive measures, is being built to achieve LEED Silver certification from the USGBC.

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.

Construction of the baggage-handling tunnel, which preceded construction of the terminal building above it, was completed in January 2011.

The metal decks and incline column phases of the project were completed in October 2011, while the slab-on-grade for the new building was finished in January 2012. Bomel employed between 25 and 30 workers during the duration of the project.

By the time it’s completed next year, Green Build will have employed between 2,500 and 3,000 construction workers. +

 

Add new comment

Your Information
Your Comment

Filtered HTML

  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <blockquote> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

Plain text

  • No HTML tags allowed.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.
Refresh Type the characters you see in this picture. Type the characters you see in the picture; if you can't read them, submit the form and a new image will be generated. Not case sensitive.  Switch to audio verification.
Overlay Init